Sacramento project record
El Camino Vision Zero Safety Project is in City planning or preliminary engineering
Sacramento Public Works lists El Camino Vision Zero Safety Project in the “Preliminary Engineering” phase. On El Camino near Sac Northern Bike Trail. Colfax Street to Empress Street. Outreach and preliminary design. Unassigned. Schedule fields are plans and may change.
- Where
- City of Sacramento · Noralto
- Status
- Proposed
- Date shown
- Watch capture date: Aug 27, 2026
- Why it matters
- This is an early official signal of a proposed physical change at a specific Sacramento location.
Open the primary official record
Then · now · next
- Then
- We first captured this official record on Aug 27, 2026.
- Now
- The latest source record we hold shows Proposed; the source did not provide a record date.
- Next
- The City map lists planned start Jan 1, 2032 and planned end Dec 31, 2032. The next documented phase would be design advancement or construction; schedule fields are plans, not promises.
Recorded timeline
No additional milestones have been captured yet.